The global AI buildout

Today Oct 2026

18.2GW is what the world's largest AI data centers draw today

drawn by the world's 95 largest AI campuses, about 43% of the world's AI computing capacity

The power of 14.8 million US homes.

Online
74
Building
21
Data-centre power use, 2025
485 TWh
AI compute worldwide
~20.0M H100e
Capex, Q2 2026
$208.4B
Cloud regions
297 in 46 countries

Data: Epoch AI, CC BY 4.0 · IEA, CC BY 4.0 · company filings · cloud providers · by country · sources

A globe of the global AI buildout. Each light is one large AI campus, its area the campus's power; rings are AI supercomputers and small squares are public cloud regions.
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X

The largest AI campuses have added 472 MW since 11 Oct 2026

Epoch's 11 Oct 2026 release against 22 Oct 2026
  1. Switched on1 site +152 MW
  2. 11 Oct 2026, restated1 site revised by Epoch +5 MW
  3. Newly tracked2 sites +315 MW
  4. Net change17.7 GW → 18.2 GW +472 MW
Facility power of the tracked sites went from 17.7 GW in Epoch's 11 Oct 2026 release to 18.2 GW on 22 Oct 2026: +152 MW switched on in between, +5 MW from Epoch restating its 11 Oct 2026 figures, and +315 MW from newly tracked sites.

Switched on · 1

  1. Anthropic-Amazon New Carlisle +152 MW 1.1 GW → 1.2 GW

Restated · 1

  1. CoreWeave Norway +5 MW 50 MW → 55 MW

Newly tracked · 2

  1. Envision Galaxy Ulanqab 612 MW projected Undisclosed · Dec 2027
  2. Bridge Data Centres MY06 315 MW ByteDance
Sites tracked
93 → 95
Drawing power
73 → 74
Projected, Jan 2030
49.0 GW → 49.9 GW

Against Epoch's release of 11 Oct 2026 (archived copy).

8 of 91 planned campus power increases have slipped or shrunk

Each planned step against the newest release
On plan
83 steps · 27.9 GW planned · at the planned size on the planned date
Later
6 steps · 711 MW planned · the planned size, on a later date
Smaller
2 steps · 2.3 GW planned · never at the planned size

The IEA expects data centers to use 950 TWh by 2030

all data centers, worldwide · IEA
2024
415 TWh
2025
485 TWh
2030 · base case
950 TWh

about 1.5% of world electricity in 2024, and around 3% by 2030. AI-focused data centers reach about 465 TWh in 2030. IEA, CC BY 4.0.

By region, 2024

  1. United States more than 4% 180 TWh
  2. China 100 TWh
  3. Europe slightly less than 2% 70 TWh
  4. Japan about 2% <20 TWh
  5. India about 0.5% 9 TWh

$208.4B of capital spending in Q2 2026, up 91% on a year earlier

9 companies · quarterly
  1. $51.5B 2024 Q1
  2. $60.6B 2024 Q2
  3. $66.7B 2024 Q3
  4. $89.8B 2024 Q4
  5. $86.0B 2025 Q1
  6. $108.9B 2025 Q2
  7. $115.9B 2025 Q3
  8. $141.8B 2025 Q4
  9. $166.2B 2026 Q1
  10. $208.4B 2026 Q2
CompanyQ2 2026A year earlierChange
Amazon US $54.2B $32.2B +68%
Alphabet US $44.9B $22.4B +100%
Microsoft US $35.8B $17.1B +110%
Meta US $30.1B $16.5B +82%
Oracle US $16.5B $9.1B +82%
Alibaba CN $10.0B $5.4B +85%
Tencent CN $8.7B $3.2B +173%
CoreWeave US $6.4B $2.5B +162%
Baidu CN $1.7B $0.5B +216%

Cash spent on property and equipment, from each company's filings, in US dollars. The last four quarters total $632.2B.

54 countries

Every country →
Country Largest campuses, today AI compute now, H100e Cloud regions
United States 15.3 GW 12.8M 52
Malaysia 1.6 GW 1.3M 6
China 848 MW 320K 34
United Kingdom 124 MW 124K 10
Indonesia 94 MW 84K 7
Finland 90 MW 49K 2
Australia 57 MW 46K 10
Norway 55 MW 51K 1
Portugal 40 MW 32K —
Iceland 7 MW 6K —
Germany — — 8
Japan — — 13
France — — 9
Switzerland — — 4
Saudi Arabia — — 5

Cloud regions by provider, live and open to all customers

  1. Microsoft Azure 49
  2. Oracle Cloud Infrastructure 45
  3. Google Cloud 43
  4. AWS 34
  5. Huawei Cloud 32
  6. Alibaba Cloud 30
  7. Tencent Cloud 21
  8. CoreWeave 21
  9. IBM Cloud 13
  10. Nebius 9

From 82 MW in 2023 to 18.2 GW today

facility power · by month
Jan 2023
82 MW
Today
18.2 GW
Jan 2030 · projected
49.9 GW
As a table
1 JanuaryFacility powerH100-equivalentsCapital costSites drawing power
2022 57 MW 8K $1.8B 1
2023 82 MW 14K $2.5B 2
2024 591 MW 213K $17.8B 7
2025 2.6 GW 1.2M $78.1B 23
2026 8.6 GW 6.0M $256.7B 46
2027 (projected) 21.9 GW 19.2M $642.4B 83
2028 (projected) 36.9 GW 42.4M $1.07T 91
2029 (projected) 49.8 GW 67.0M $1.44T 95
2030 (projected) 49.9 GW 67.2M $1.45T 95

The largest, today

by facility power

TodayProjected peak

  1. 01 Colossus 2 SpaceXAI · Memphis, Tennessee 1.3 GW → 2.1 GW
  2. 02 Anthropic-Amazon New Carlisle Amazon · New Carlisle, Indiana 1.2 GW → 2.3 GW
  3. 03 Microsoft Fairwater Atlanta Microsoft · Fayetteville, Georgia 859 MW
  4. 04 DayOne Nusajaya Undisclosed · Johor Bahru, Johor, Malaysia 662 MW
  5. 05 Meta Prometheus Meta · New Albany, Ohio 612 MW → 1.3 GW
  6. 06 DayOne Kempas Undisclosed · Kempas, Johor, Malaysia 590 MW
  7. 07 OpenAI Stargate Abilene Oracle · Abilene, Texas 590 MW → 1.2 GW
  8. 08 Microsoft Fairwater Wisconsin Microsoft · Mount Pleasant, Wisconsin 442 MW → 2.7 GW
  9. 09 Google Pryor (North) Google · Pryor, Oklahoma 442 MW
  10. 10 Colossus 1 SpaceXAI · Memphis, Tennessee 425 MW → 442 MW
  11. 11 Google New Albany Google · New Albany, Ohio 400 MW
  12. 12 CoreWeave Denton TX CoreWeave · Denton, Texas 367 MW → 395 MW
  13. 13 Google Columbus Google · Columbus, Ohio 364 MW → 464 MW
  14. 14 Amazon Madison Mega Site Amazon · Canton, Mississippi 341 MW → 819 MW
  15. 15 QTS Richmond 1 Undisclosed · Sandston, Virginia 333 MW

The United States holds 84% of the largest campuses' power

facility power today

By owner

  1. Google 3.9 GW
  2. Meta 2.9 GW
  3. Undisclosed 2.3 GW
  4. Amazon 2.3 GW
  5. Microsoft 2.0 GW
  6. SpaceXAI 1.7 GW
  7. CoreWeave 955 MW
  8. Oracle 684 MW
  9. Huawei 393 MW
  10. ByteDance 315 MW
  11. 7 others 826 MW

By country

  1. United States 15.3 GW
  2. Malaysia 1.6 GW
  3. China 848 MW
  4. United Kingdom 124 MW
  5. Indonesia 94 MW
  6. Finland 90 MW
  7. Australia 57 MW
  8. Norway 55 MW
  9. Portugal 40 MW
  10. Iceland 7 MW

US data-center building rises 73% in a year, to $85.0 bn a year

Construction spending, with every revision

U.S. Census Bureau, Construction Spending, release of 1 October 2026, public domain. Buildings only, without the servers inside. August 2026 is Census’s preliminary estimate, and the next two releases will revise it. The level, the change on a year earlier and the revisions.

All 95 sites

Download CSV
Site Owner Where Today Projected peak
Colossus 2 SpaceXAI Memphis, Tennessee 1.3 GW 2.1 GW · Feb 2027
Anthropic-Amazon New Carlisle Amazon New Carlisle, Indiana 1.2 GW 2.3 GW · Mar 2028
Microsoft Fairwater Atlanta Microsoft Fayetteville, Georgia 859 MW —
DayOne Nusajaya Undisclosed Johor Bahru, Johor, Malaysia 662 MW —
Meta Prometheus Meta New Albany, Ohio 612 MW 1.3 GW · Jul 2028
DayOne Kempas Undisclosed Kempas, Johor, Malaysia 590 MW —
OpenAI Stargate Abilene Oracle Abilene, Texas 590 MW 1.2 GW · Nov 2026
Microsoft Fairwater Wisconsin Microsoft Mount Pleasant, Wisconsin 442 MW 2.7 GW · May 2028
Google Pryor (North) Google Pryor, Oklahoma 442 MW —
Colossus 1 SpaceXAI Memphis, Tennessee 425 MW —
Google New Albany Google New Albany, Ohio 400 MW —
CoreWeave Denton TX CoreWeave Denton, Texas 367 MW 395 MW · May 2027
Google Columbus Google Columbus, Ohio 364 MW 464 MW · Jul 2027
Amazon Madison Mega Site Amazon Canton, Mississippi 341 MW 819 MW · Mar 2028
QTS Richmond 1 Undisclosed Sandston, Virginia 333 MW —
Bridge Data Centres MY06 ByteDance Kulai, Johor, Malaysia 315 MW —
Google Bristow Google Bristow, Virginia 286 MW —
Google Omaha Google Omaha, Nebraska 284 MW 474 MW · Jul 2028
Google Council Bluffs (East) Google Council Bluffs, Iowa 284 MW —
Google Papillion Google Papillion, Nebraska 284 MW —
Amazon Ridgeland Amazon Ridgeland, Mississippi 273 MW 1.0 GW · Sep 2028
Microsoft Goodyear Microsoft Goodyear, Arizona 263 MW —
AWS New Albany Amazon New Albany, Ohio 255 MW 405 MW · Jul 2027
VNET Bayin Ulanqab VNET Ulanqab, Inner Mongolia, China 252 MW 798 MW · Sep 2027
QTS Richmond 2 Undisclosed Sandston, Virginia 252 MW —
Meta-QTS Hillsboro 2 Meta Hillsboro, Oregon 243 MW —
Meta Jeffersonville Meta Jeffersonville, Indiana 241 MW —
Meta Rosemount Meta Rosemount, Minnesota 241 MW —
Google Mesa Google Mesa, Arizona 237 MW —
Meta Temple Meta Temple, Texas 231 MW —
Microsoft Project Osmium Microsoft Cumming, Iowa 228 MW —
Google Storey County Google Clark, Nevada 214 MW 389 MW · Jun 2027
Huawei Horinger Huawei Hohhot, Inner Mongolia, China 212 MW 415 MW · Feb 2028
Alibaba Zhangbei Alibaba Zhangbei, Hebei, China 203 MW —
QTS Richmond 3 Undisclosed Sandston, Virginia 202 MW 336 MW · Feb 2027
Coreweave Helios CoreWeave Afton, Texas 200 MW 800 MW · Jan 2029
Meta Montgomery Meta Montgomery, Alabama 199 MW 465 MW · Feb 2027
Meta Huntsville Meta Huntsville, Alabama 198 MW —
Meta Kuna Meta Kuna, Idaho 198 MW —
Google The Dalles Google The Dalles, Oregon 185 MW —
Meta Cheyenne Meta Cheyenne, Wyoming 182 MW 249 MW · Feb 2027
Huawei Wuhu Huawei Wuhu, Anhui, China 181 MW 526 MW · Dec 2027
Meta Eagle Mountain Meta Eagle Mountain, Utah 179 MW —
Google Lincoln Google Lincoln, Nebraska 170 MW 339 MW · Oct 2027
Google Lancaster Google Lancaster, Ohio 164 MW —
AWS Berwick Amazon Berwick, Pennsylvania 139 MW 212 MW · Aug 2027
Google Kansas City East Google Kansas City, Missouri 126 MW —
Google Waltham Cross Google Cheshunt, Hertfordshire, United Kingdom 124 MW —
Google Midlothian Google Midlothian, Texas 123 MW —
STACK Infrastructure NVA02 Undisclosed Manassas, Virginia 118 MW 487 MW · Jan 2028
Meta Los Lunas Meta Los Lunas, New Mexico 114 MW 273 MW · Jan 2028
CoreWeave Chester VA CoreWeave Chester, Virginia 114 MW 197 MW · Jun 2027
Meta Gallatin Meta Gallatin, Tennessee 114 MW —
Microsoft SAT40 Microsoft San Antonio, Texas 106 MW —
Meta Sarpy Meta Springfield, Nebraska 105 MW —
Oracle Batam Oracle Batam, Riau Islands, Indonesia 94 MW —
Google Red Oak Google Red Oak, Texas 93 MW 185 MW · Dec 2026
Google Arcola Google Arcola, Virginia 93 MW —
CoreWeave Marble NC CoreWeave Marble, North Carolina 91 MW —
Nebius Mantsala Nebius Mantsala, Uusimaa, Finland 90 MW 196 MW · Dec 2027
Meta Aiken Meta Aiken, South Carolina 90 MW 168 MW · Nov 2026
CoreWeave Ellendale ND CoreWeave Ellendale, North Dakota 88 MW 520 MW · Jun 2027
Stream Phoenix Undisclosed Goodyear, Arizona 77 MW 267 MW · Jan 2030
Microsoft-Nebius New Jersey Nebius Vineland, New Jersey 70 MW —
Microsoft SAT14 Microsoft San Antonio, Texas 66 MW —
Core42 Lake Mariner Core42 Barker, New York 58 MW —
Southgate Melbourne Firmus Melbourne, Victoria, Australia 57 MW —
CoreWeave Norway CoreWeave Øvrebø, Agder, Norway 55 MW —
Anthropic Lake Mariner AI XPV Platform Barker, New York 49 MW 441 MW · Mar 2027
Vantage TX1 Undisclosed San Antonio, Texas 45 MW 179 MW · Aug 2027
Start Campus Sines Data Campus Nscale Sines, Setúbal, Portugal 40 MW 280 MW · Sep 2027
CoreWeave Dalton 1 & 2 CoreWeave Dalton, Georgia 40 MW —
xAI QTS Atlanta SpaceXAI Atlanta, Georgia 24 MW —
Nscale Keflavik Nscale Reykjanesbær, Suðurnes, Iceland 7 MW 13 MW · Dec 2026
OpenAI Stargate New Mexico Oracle Santa Teresa, New Mexico Building 2.5 GW · Dec 2028
Meta Hyperion Meta Holly Ridge, Louisiana Building 2.2 GW · Jan 2028
OpenAI Stargate Shackelford Oracle Abilene, Texas Building 2.0 GW · Nov 2028
QTS Cedar Rapids Undisclosed Cedar Rapids, Iowa Building 1.6 GW · Nov 2027
OpenAI Stargate UAE G42 Abu Dhabi, Abu Dhabi, United Arab Emirates Building 1.4 GW · Jan 2028
OpenAI Stargate Michigan Oracle Benton, Michigan Building 1.4 GW · Dec 2028
OpenAI Stargate Wisconsin Oracle Port Washington, Wisconsin Building 1.3 GW · Dec 2028
Goodnight Google Claude, Texas Building 1.3 GW · Oct 2027
OpenAI Stargate Milam Softbank Burlington, Texas Building 1.2 GW · Dec 2028
Google Fort Wayne Google Fort Wayne, Indiana Building 1.0 GW · Jun 2028
Crusoe Abilene Expansion Microsoft Abilene, Texas Building 941 MW · Nov 2027
Envision Galaxy Ulanqab Undisclosed Ulanqab, Inner Mongolia, China Building 612 MW · Dec 2027
Meta Bowling Green Meta Bowling Green, Ohio Building 570 MW · Jan 2028
QTS Eagle Mountain Meta Eagle Mountain, Utah Building 411 MW · Jul 2027
Google Cedar Rapids Google Cedar Rapids, Iowa Building 314 MW · May 2027
Anthropic Barber Lake Cipher Mining Colorado City, Texas Building 300 MW · Apr 2027
OpenAI Stargate Lordstown Softbank Lordstown, Ohio Building 300 MW · Mar 2027
CoreWeave Muskogee OK CoreWeave Muskogee, Oklahoma Building 181 MW · Dec 2027
CoreWeave Lancaster Greenfield site CoreWeave Lancaster, Pennsylvania Building 124 MW · Jun 2027
Microsoft Narvik Norway Nscale Bjerkvik, Narvik, Norway Building 124 MW · Dec 2026
EcoDataCenter 2 Mistral AI Borlänge, Dalarna County, Sweden Building 67 MW · Jun 2028