SpaceXAI · Memphis, Tennessee

Colossus 2

1.3GW

The power of 1.0 million US homes.

Drawing power since Oct 2025. Projected to reach 2.1 GW by Feb 2027.

Capital cost
$35.8B
Chips
B200, B300
Users
Anthropic, Cursor, SpaceXAI
Embed

Each frame credits Epoch AI and links back to its page. Preview it.

Cite
Download
Post on X
Colossus 2 on a globe of the world's largest AI data centers.

Power over time

facility power · 7 milestones
Every milestone
  1. 28 Feb 2025 — Land clearing begins next to the existing building.
  2. 8 Sep 2025 — Battery facility connected to the building. 121 air-cooled chillers installed, which could support 200 MW. In the Duke faciltiy in nearby Mississippi, several natural gas turbines are in place but not fully connected up.
  3. 19 Oct 2025 323 MW Battery facility looks complete (though more might be added). Turbines look connected up, minimal construction around them. We believe this state corresponds to the first compute cluster brought online at this site of "approximately 110,000 GB200 processors, approximately 210 megawatts of compute power", as detailed in the company S-1 filing, page 76. Based on those numbers, we believe "compute power" corresponds to GPU server power. Earlier tweets from Elon Musk also support this timing, and it's consistent with the estimated cooling capacity based on the satellite image.
  4. 13 Jan 2026 323 MW Since October, an array of dry cooling air-cooled condensers has been added (the array of large fans to the left of the building), and appears almost complete. Two more similar arrays appear to be under construction. More air-cooled chillers, batteries, and gas turbines have also been installed.
  5. 6 Apr 2026 661 MW The first array of dry cooling air-cooled condensers for Building 1 has been completed and is operational. A second array, with larger fans, is about halfway complete (located to the south of the first array). More chillers have also been added. For Building 2, an array of dry cooling air-cooled condensers of the same type as Building 1's first array is beginning construction. We believe this corresponds to the "second cluster of 110,000 GB300 processors and 220 megawatts of compute power" from the company S-1 filing, page 76, with compute power corresponding to GPU server power. This is also consistent with our estimates based on cooling equipment.
  6. 15 Jun 2026 1.3 GW The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.
  7. 25 Feb 2027 · projected 2.1 GW Building 3 is estimated to be completed. The site is predicted to have enough power infrastructure installed for a total of 1.5 GW of IT Power. Based on building plans we predict the addition of three more cooling arrays similar to the 6x24 dry coolers near Building 1 and 2. With the completion of current cooling structures and the addition of these arrays there will be ~540MW more cooling capacity for a full facility total of ~1390MW. If this cooling capacity is supplemented by mobile coolers, there would be enough cooling and power infrastructure to support 1.5 GW of IT power.

Every step Epoch planned here on 2 Sep 2026 is still on plan. Planned against reached

Nuclear made 41% of the power on this site's grid

net generation by fuel · Oct 2025 to Sep 2026

Tennessee Valley Authority TVA · balancing authority

  1. Gas 33%
  2. Coal 16%
  3. Nuclear 41%
  4. Wind 0%
  5. Solar 2%
  6. Hydro 7%
  7. Other <1%

The grid of the utilities that serve Shelby County, TN. Each grid is a balancing authority. Generation only; imports are excluded. Every grid behind an AI site.

Owners plan 16 MW of new power in Shelby County, all solar

power plants in Shelby County · EIA-860M, September 2026
  1. SR Shelby Solar · 10 MW · Dec 2027 · proposed · SR Shelby, LLC
  2. SR Shelby II, LLC Solar · 6 MW · Feb 2028 · proposed · SR Shelby II, LLC

In service in Shelby County today: 1.6 GW. Since January 2023: 225 MW added, 502 MW retired. A plant in the same county does not mean it feeds the site. Power plants near every AI site.

Sources

selected by Epoch AI
  1. WSJ profile of the Colossus data centers
  2. Final GPU count reported by Elon Musk
  3. MLGW update mentioning power requests for Colossus 2
  4. SpaceX-Cursor partnership to use Colossus
  5. Anthropic to use Colossus 2 from June 2026
  6. SpaceX S-1 filing, mentioning exact compute and power for Colossus 2

Data: Epoch AI, “AI data centers”, CC BY 4.0, retrieved 22 Oct 2026. Facility power adds cooling and other overhead to the IT power the servers draw. Placed at the centre of Memphis. Grid: U.S. Energy Information Administration, Hourly Electric Grid Monitor (Form EIA-930), public domain, retrieved 16 Oct 2026; utilities by county from Form EIA-861 and the U.S. Census Bureau Geocoder, public domain. Power plants: U.S. Energy Information Administration, Form EIA-860M, public domain, inventory as of September 2026. All sources.